Portfolio overview

J. Roche — Engineering Manager

Ardmore Processing Facility

Total projects

18

4 engineers

On track

9

50% of portfolio

Blocked

2

require escalation

Open actions

11

3 due this week

AM

A. Murphy

Electrical & Instrumentation

5 projects1 blocked4 constraints
ProjectStatusProgressNext milestoneConstraint

Transformer Protection Relay Upgrade

APF-2026-011

Active
45%
Relay FAT — Aug 2026Protection relay 16 wk delivery on critical path

SCADA Communications Refresh

APF-2026-015

Blocked
30%
IT security approvalIT security review stalled — 6 weeks

Perimeter Security System Install

APF-2026-019

In review
20%
Tender award — Jul 2026

UPS Replacement — Control Building

APF-2026-023

Active
60%
Factory witness — Sep 2026Battery module scope change under review

Variable Speed Drive Upgrade

APF-2026-031

Planning
10%
Design freeze — Oct 2026Drive hardware 18–20 wk lead time
DB

D. Brennan

Process & Mechanical

5 projects2 constraints
ProjectStatusProgressNext milestoneConstraint

Heat Recovery Steam Generator Overhaul

APF-2026-008

Active
75%
Commissioning — Jul 2026

Condensate Return Pump Replacement

APF-2026-012

Complete
100%
Closed out

Nitrogen Generation System Upgrade

APF-2026-017

Active
55%
Outage window — Aug 2026Outage window TBC with Operations

Process Water Treatment Expansion

APF-2026-022

Planning
15%
Budget approvalCapex budget approval pending

Pressure Vessel Inspection — V-Series

APF-2026-027

In review
35%
FEED complete — Jul 2026
SO

S. O'Connor

Civil & Structural

4 projects1 blocked3 constraints
ProjectStatusProgressNext milestoneConstraint

Secondary Substation Relocation

APF-2026-009

Active
40%
Vendor pricing — Jul 20262 of 4 vendor quotes outstanding

Administration Block HVAC Replacement

APF-2026-014

Active
65%
Installation — Aug 2026

Warehouse Structural Remediation

APF-2026-020

Blocked
25%
Planning permissionPlanning permission outstanding — 9 weeks

Loading Bay Canopy Extension

APF-2026-028

Planning
5%
Structural survey — Sep 2026Structural survey not yet scheduled
CW

C. Walsh

Instrumentation & Control

4 projects1 constraints
ProjectStatusProgressNext milestoneConstraint

Custody Transfer Metering Upgrade

APF-2026-007

Active
50%
Field install — Sep 2026Fiscal meter 12 wk lead time

Turbine Hall Vibration Monitoring

APF-2026-013

Active
45%
FAT — Aug 2026

Integrated Fire & Gas System Upgrade

APF-2026-018

In review
30%
Design review — Jul 2026

Field Instrument Audit & Tagging

APF-2026-024

Complete
100%
Closed out